IMCA has reported an incident in which rigging was recovered to deck with missing parts. The incident occurred when a rigging composed of two tri-plates was recovered to the vessel deck, and crew noticed that a nut was missing from one of the shackles.
The installation rigging included two tri-plates, one in the lower section of the rigging arrangement just above the suction pile, and the second one on the upper end of the rigging arrangement connected to the crane’s auxiliary block.
The shackle from which the nut was missing was one of the three installed in the upper tri-plate which was used to transfer the pile from the crane auxiliary block to the Abandonment & Recovery (A&R) winch when lowering the pile to the seabed.
Investigation noted the following:
- The cotter pin (split pin) was incorrectly installed (not opened out enough);
- There was no thorough visual inspection of tri-plate shackles by rigging crews (onshore or offshore);
- The tri-plate was secured on deck with shackles facing downward;
- The pre-sail-away checklist did not include checks of tri-plate shackles;
- The offshore rigging crew were unaware of observation following previous pile installation;
- There was a lack of training of onshore rigging team provided for barge mobilization.
The following root causes were identified:
- Environment – rigging arrangement not allowing straightforward inspection of cotter pins;
- People – lack of communication between onshore/offshore and project/vessel teams. Onshore project team were aware of the prior observance of a similar hazard. A presentation was developed and meeting held on shore but no evidence could be found that it was ever shared with the teams on board the vessel;
- People – lack of attention/due care/poor work practice. Lack of pre-lift check of shackles by riggers, and failure to fully check rigging prior to barge sail-away;
- Organization – failure to vet the onshore rigging team supplied by co-contractor’s subcontractor.
Actions taken:
- Inspection of all rigging arrangements on the other piles;
- Reviewed pre-sail-away checklist and integrated into it all specific checks such as nuts and securing cotter pins;
- Updated the risk assessment and lift plan to reflect the hazards of missing/incorrectly installed pins in shackles;
- Onshore and offshore riggers to check thoroughly the presence of securing cotter pins after installation and before lifting operations;
- Project team to ensure that subcontractor’s rigging teams are properly vetted for competency prior to future barge mobilizations.
Source & Image Credit: IMCA Safety Flash