Freeport LNG announced the start of commercial operations for the second of its three liquefaction trains, with the commencement of gas deliveries from BP under its 20-year tolling agreement with Freeport.
Freeport LNG’s Train 1 began commercial operations last month, with the commencement of Osaka Gas’ and JERA’s tolling agreements.
The Train 2 of the Freeport LNG project began producing its first LNG fuel in early December and the cargo was shipped in mid-December.
Freeport’s electric drive motors not only reduce emissions by over 90% relative to other plants which use combustion turbines, they should also require less maintenance with less downtime. The performance test on Train 2 was completed in only 37 days after first gas was delivered to the liquefaction facilities, down from 107 days on Train 1. We are extremely pleased with the current operational efficiency and performance from both trains,
… said Michael Smith, Founder, Chairman and CEO, Freeport LNG.
Construction on Freeport’s Train 3 is essentially complete.
Gas has been introduced to the pre-treatment facilities and the Company expects Federal Energy Regulatory Commission (FERC) approval to bring gas to the liquefaction site next month.
Train 3 remains on track for a commercial start date in May.
Freeport LNG Development, L.P. was formed in 2002 to develop, own and operate an LNG terminal on Quintana Island, near Freeport, Texas.
The terminal started LNG import operations in June 2008 and began LNG export operations in 2019.
Freeport LNG claims to be implementing the largest fully electric motor drive natural gas liquefaction plant in the world, reducing emissions at the facility by over 90% relative to other plants which use combustion turbines.