IMCA informs about an incident where, a chain hoist failure resulted in a chain link breaking which caused an 800kg load to fall to deck.
The incident
A chain hoist failure resulted in a chain link breaking which caused an 800kg load to fall to deck from a height of 1 metre. Personnel were working on a wind turbine foundation.
[smlsubform prepend=”GET THE SAFETY4SEA IN YOUR INBOX!” showname=false emailtxt=”” emailholder=”Enter your email address” showsubmit=true submittxt=”Submit” jsthanks=false thankyou=”Thank you for subscribing to our mailing list”]
A regular shaped load was being moved out of the tower using a chain block suspended from a cantilevered trolley beam on a temporary gantry structure erected on the site.
A lifting bag was positioned beneath the gantry structure onto which to lower the winch. When the winch was 1 metre above the lifting bag, one of the chain links on the main chain hoist failed causing the load to fall. No-one was in the line of fire; no-one was injured.
Probable cause
Findings indicated that at some point during the operation, the chain had entered the hoist in a twisted or knotted configuration and excessive force applied resulted in damage to the chain link which subsequently failed.
- Insufficient attention was given to ensuring that the chain between the block and the load was not twisted or in a knotted configuration;
- The headroom between the gantry beam and the tower floor was less than expected which resulted in the chain hook having to be pulled as tightly into the block as possible to keep the load clear of the floor. This put additional load into the chain and block and left nowhere for any residual twist in the chain to go, causing the damage to the chain and its subsequent failure.
Lessons learned
When using a chain hoist, consider checking the chain for twists as it enters the block. Continually monitor the chain to ensure no twisting occurs. Avoid pulling the hook into the body of the hoist.