Following the latest version of IMCA’s Safety Flashes, it is noted a case where during offshore operations, crane wire parted causing the load to fall to the sea.
The incident
A concrete mattress was being deployed as part of the construction of a pipeline crossing. As the load was swung outboard and before it entered the water, the crane wire parted causing the load to fall to the seabed.
The vessel was in a safe handling zone more than 5m from subsea assets. The mattress was overboarded when the crane was 17m from the nearest subsea asset.
The vessel’s main crane was being used to overboard a 6m x 3m x 0.5m concrete mattress, (15.8Te) + lifting frame (1.7Te). Mattress number 6 was deployed in a series of 15, as part of the crossing construction.
[smlsubform prepend=”GET THE SAFETY4SEA IN YOUR INBOX!” showname=false emailtxt=”” emailholder=”Enter your email address” showsubmit=true submittxt=”Submit” jsthanks=false thankyou=”Thank you for subscribing to our mailing list”]
The crossing was being built to allow a new pipeline to be laid which passed over a buried 3rd party gas pipeline.
During the lift, the load was swung outboard and before it entered the water, the crane wire parted causing the load to fall to the seabed. The mattress and lifting frame were found 6m away from the buried gas pipeline.
Findings
According to IMCA:
Procedures were not followed, and decisions were made without having the full facts or understanding of operations.
- The vessel main crane was in use during the period following the Magnetic Rope Testing (MRT) when the results were still being evaluated. The test results stated a clear recommendation to cut back the wire;
- The operational limit was set on using 30% of the crane capacity. There was a misunderstanding that the Safe Working Load (SWL) of the crane wire was 60Te;
- There was no process within the company’s Wire Rope Integrity Management Procedure that provided an option for application of an operational limit to deteriorating wires;
- No management of change process was applied to control the application and understanding of an operational limit, this may have triggered the involvement of the compny’s lifting experts ashore;
- No-one on the vessel questioned the operational limit, how it should be interpreted or how it applied to the crane load charts;
- There was no communication of the crane operational limits to the project team, subsequently this was not included in the worksite risk assessment review for the mobilisation and offshore operations.
Lessons learned
- Ensure full communication and engagement between shore-side experts and management on the one hand, and vessel team on the other;
- Any dispensation for wire ropes should be recorded in planned maintenance systems;
- Ensure that mattresses are moved into position from a direction that prevents the mattress being lifted over existing pipelines;
- Reinforce the requirements for the consistent application of the management of change, and technical management of change.
See also:
Lessons learned: Crewman crushed from fall of secured material
Lessons learned: Containers lost in heavy weather due to stiff vessel