An initial survey refers to a complete inspection conducted before a ship is put into service, encompassing all items relating to a particular certificate. This ensures that the relevant requirements are complied with and that these items are satisfactory for the intended service of the ship.
Additionally, more surveys are often required to ensure continued compliance with regulations. Let’s explore how many can take place onboard!
Types of survey used
#1 Initial survey
It is a complete inspection before a ship is put into service of all the items relating to a particular certificate.
The initial survey should be held before the ship is put in service, or when a new instrument applies to an existing ship, and the appropriate certificate is issued for the first time.
#2 Annual survey
It should be held within three months before or after each anniversary date of the certificate
#3 Intermediate survey
It is an inspection of specified items relevant to the particular certificate to ensure that they are in a satisfactory condition
The intermediate survey should be held within three months before or after the second anniversary date or within three months before or after the third anniversary date of the appropriate certificate and should take the place of one of the annual surveys
#4 Periodical survey
It is an inspection of the items relating to the particular certificate to ensure that they are in a satisfactory condition and fit for the service for which the ship is intended.
The periodical survey should be held within three months before or after the second anniversary date or within three months before or after the third anniversary date in the case of the cargo ship safety equipment certificate and should take the place of one of the annual surveys; in the case of the cargo ship safety radio certificate,it should be held within three months before or after each anniversary date
#3 Renewal survey
It is the same as a periodical survey but also leads to the issue of a new certificate.
The renewal survey should be held before the appropriate certificate is renewed. The cargo ship safety construction renewal survey may be commenced at the fourth annual survey and may be progressed during the succeeding year with a view to completion by the fifth anniversary date. The survey items of the fourth annual survey should not be credited to the completion of the renewal survey.
#4 Additional survey
The additional survey should be held: when required after an investigation; or whenever any important repairs or renewals are made; or when ballast water management systems (BWMS) are retrofitted on an
existing ship to which an International Ballast Water Management Certificate was previously issued.
In cargo ships…
#5 Inspections of the outside of the ship’s bottom of cargo ships
There should be a minimum of two inspections of the outside of the ship’s bottom during any five-year period, except where SOLAS 74/88 regulation I/14(e) or (f) is applicable. One such inspection should be carried out on or after the fourth annual survey in conjunction with the renewal of the Cargo Ship Safety Construction Certificate or the Cargo Ship Safety Certificate.
Where the Cargo Ship Safety Construction Certificate or the Cargo Ship Safety Certificate has been extended under SOLAS 74/88 regulation I/14(e) or (f), this five-year period may be extended to coincide with the validity of the certificate. In all cases the interval between anytwo such inspections should not exceed 36 months.
Other types of surveys
- Survey of radio installations: The survey of the radio installations, including those used in life-saving appliances, should always be carried out by a qualified radio surveyor who has necessary knowledge of the requirements of SOLAS 74, the International Telecommunication Union’s Radio Regulations and the associated performance standards for radio equipment. The radio survey should be carried out using suitable test equipment capable of performing all the relevant measurements required by these Guidelines. On satisfactory completion of the survey, the radio surveyor should forward a report of the survey, which should also state the organization he or she represents, to the authorities responsible for the issue of the ship’s Cargo Ship Safety Radio Certificate or Passenger Ship Safety Certificate.
- Survey of the automatic identification system (AIS): The survey of the automatic identification system should always be carried out by aqualified radio surveyor who has necessary knowledge of the requirements of SOLAS 74,the International Telecommunication Union’s Radio Regulations and the associated performance standards for radio equipment. The survey of the automatic identification system should be carried out using suitable test equipment capable of performing all the relevant measurements required by and in accordance with the Guidelines on annual testing of the automatic identification system (AIS) (MSC.1/Circ.1252).
- Surveys for ships intended to operate in polar waters: In accordance with SOLAS 74/88 regulations XIV/2.1 and 3.1, MARPOL Annex I regulation 47, MARPOL Annex II regulation 22, MARPOL Annex IV regulation 18 and MARPOL Annex V regulation 14, the Polar Code is a standalone instrument, providing requirements additional to SOLAS 74/88 and MARPOL for ships intended to operate in polar waters. The requirements of the Polar Code should be surveyed in the context of the surveys under SOLAS 74/88 and MARPOL, but do not form separate survey types.
- Remote surveys: A remote survey is a means of survey that enables examination of a ship’s hull structure, machinery components and systems, and ship’s equipment and/or gathering information and evidence of compliance with applicable requirements without the physical attendance on board of the surveyor. In the absence of a surveyor on board, the examination and tests are carried out by a competent crew member and/or a qualified technician of an approved service supplier under the remote supervision and instructions of the surveyor by two-way audio and video communication or other accepted means of communication and to the satisfaction of the surveyor.